Plant Floor

Book companion resource · Worksheet

MTTR Analysis Worksheet

Letter & A4. Print-ready. Free, no email required.

← Back to toolkit · Browse by chapter

Find the asset-failure-mode combinations driving your availability loss, diagnose what makes them slow, and track job plan and parts readiness for the top three.

Companion to: Fix the System, Chapter 23. Who uses it: the maintenance manager, planner, and reliability engineer. When to use: at the start of the Downtime Reduction playbook, then monthly until availability stabilizes above 97%.

Plant / Line: _______________________ Date: _______________________ Completed by: _______________________


PART 1 — Downtime Event Log (Last 6 Months)

Pull all unplanned downtime events. Record asset, failure mode, and total MTTR. Sort by total downtime hours contributed — not by frequency.

Event #DateAssetFailure ModeStart TimeEnd TimeMTTR (hrs)Primary Delay Cause

Primary Delay Cause codes:

  • PRT — Waiting for parts
  • DX — Diagnosis / troubleshooting time (unclear failure mode)
  • SKL — Waiting for technician with specific skill
  • ACC — Access, permit, or LOTO delay
  • RWK — Rework from incorrect first repair

PART 2 — Top 3 Asset-Failure-Mode Combinations

Group events from Part 1 by asset-failure-mode combination. Calculate total downtime hours per combination. Rank and select the top 3.

RankAssetFailure Mode# of EventsTotal Downtime HoursAvg MTTRDominant Delay Code
1
2
3
4
5

Top 3 account for ______% of all downtime hours.

Focus the next 90 days on the top 3 only. Address 4 and 5 in the following quarter.


PART 3 — Job Plan Readiness Assessment

For each of the top 3 combinations, assess the current job plan state.

Combination 1: _______________________

Assessment ItemStatusGap / Action
Job plan exists in CMMS☐ Yes ☐ No ☐ Outdated
Step sequence matches actual repair method☐ Yes ☐ No ☐ Unknown
Parts list complete with part numbers and quantities☐ Yes ☐ No ☐ Partial
Time estimate reflects actual repair duration☐ Yes ☐ No ☐ Unknown
"Most common errors" section included☐ Yes ☐ No
LOTO / isolation procedure current☐ Yes ☐ No ☐ Missing

Job plan action required: ☐ Write new ☐ Rewrite existing ☐ Minor update ☐ None


Combination 2: _______________________

Assessment ItemStatusGap / Action
Job plan exists in CMMS☐ Yes ☐ No ☐ Outdated
Step sequence matches actual repair method☐ Yes ☐ No ☐ Unknown
Parts list complete with part numbers and quantities☐ Yes ☐ No ☐ Partial
Time estimate reflects actual repair duration☐ Yes ☐ No ☐ Unknown
"Most common errors" section included☐ Yes ☐ No
LOTO / isolation procedure current☐ Yes ☐ No ☐ Missing

Job plan action required: ☐ Write new ☐ Rewrite existing ☐ Minor update ☐ None


Combination 3: _______________________

Assessment ItemStatusGap / Action
Job plan exists in CMMS☐ Yes ☐ No ☐ Outdated
Step sequence matches actual repair method☐ Yes ☐ No ☐ Unknown
Parts list complete with part numbers and quantities☐ Yes ☐ No ☐ Partial
Time estimate reflects actual repair duration☐ Yes ☐ No ☐ Unknown
"Most common errors" section included☐ Yes ☐ No
LOTO / isolation procedure current☐ Yes ☐ No ☐ Missing

Job plan action required: ☐ Write new ☐ Rewrite existing ☐ Minor update ☐ None


PART 4 — Parts Staging Readiness

For each of the top 3 combinations, verify parts staging.

CombinationParts List Verified?Parts in Dedicated Location?Location / LabelQty Sufficient for 1 Repair?Last Verified Date
1:☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
2:☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
3:☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No

Rule: Parts for top failure scenarios must be in a dedicated, labeled location — not in the general storeroom requiring a pick list. Available without a retrieval process at any hour.


PART 5 — Technician Coverage Matrix

For each of the top 3 combinations, identify which technicians can execute the repair independently (not just assist).

Target: Minimum 2 technicians per shift who can execute the repair independently.

CombinationDay ShiftAfternoon ShiftNight ShiftCoverage Gap?
1:Names:Names:Names:☐ Yes ☐ No
2:Names:Names:Names:☐ Yes ☐ No
3:Names:Names:Names:☐ Yes ☐ No

For each coverage gap: identify the cross-training candidate and the target completion date.

CombinationTechnician to TrainTrainerMethodTarget DateCompleted
☐ Shadowed ☐ Executed with guide ☐ Executed independently
☐ Shadowed ☐ Executed with guide ☐ Executed independently
☐ Shadowed ☐ Executed with guide ☐ Executed independently
☐ Shadowed ☐ Executed with guide ☐ Executed independently
☐ Shadowed ☐ Executed with guide ☐ Executed independently
☐ Shadowed ☐ Executed with guide ☐ Executed independently

Note: Training is complete when the technician executes the repair independently using the job plan. Shadowing alone does not count.


PART 6 — 90-Day Availability Tracker

WeekScheduled HoursUnplanned Downtime HoursAvailability %Top Failure Mode This WeekMTTR
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13

Formula: Availability % = (Scheduled Hours − Unplanned Downtime Hours) ÷ Scheduled Hours × 100

Benchmarks:

  • Below 95%: Critical. Apply this playbook immediately. Segment by failure mode before any other action.
  • 95–96.9%: Recovering. Identify remaining top failure-mode contributors and address in sequence.
  • 97–98.4%: Target range. Focus on first-time fix rate and job plan coverage.
  • 98.5%+: World-class. Sustain through job plan discipline and technician coverage maintenance.

From Fix the System by Ivan Getov. Companion to Chapter 23: Playbook 9 — Downtime Reduction. getov.xyz/toolkit/fix-the-system/ch23/mttr-analysis. Free. No email required.