Plant Floor

Book companion resource · Worksheet

Loss List and System Priority Worksheet

Letter & A4. Print-ready. Free, no email required.

← Back to toolkit · Browse by chapter

The Ray and Carl whiteboard, made printable. Takes an observed wrench-time loss, maps it to the system that would close it, and builds a ninety-day system-installation priority order.

Companion to: Fix the System, Chapter 2. Prerequisite: complete the Follow-a-Crew Field Audit Sheet (Ch1 companion) first. This worksheet consumes its output. How long it takes: four to six hours across two weeks of plant walking, plus two hours of prioritization at the end. What you'll produce: a ranked list of the top six systems to install in the next ninety days, with estimated hours of wrench-time recovery per system, rolled up to annual mechanic-equivalent capacity.


The logic

Your Chapter 1 field audit produced a cause-of-loss list. This worksheet takes that list and does three things:

1. Groups the causes into specific, installable systems. 2. Estimates how many wrench-time hours per week each system, if installed, would recover. 3. Ranks the systems by recovery size so you know which to install first.

At the end, you will have a number you can take to a plant manager. We are paying for X mechanic-hours of capacity and extracting Y. If we install these six systems over the next ninety days, we recover Z.

That number is the language that makes cost-cutters put their scissors down.


Part 1 — The loss list

Transfer every observed cause of non-wrench time from your field audit into the table below. One row per distinct cause. Be specific. "Waiting for parts" is not a cause. "Waiting for parts because the kit was pulled Friday and not restocked" is a cause.

#Observed loss (specific)Where it happenedHow often per week (estimate)Hours lost per week (estimate)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Ray's list had nineteen items after his Wednesday. Most plants land between 15 and 30. If your list has fewer than 10, you probably haven't walked enough shifts — add a second day and rebuild.


Part 2 — Map loss to system

For each row above, write the specific system that would close that loss if it were installed and held. Use the reference table below as a starter kit. A system might close multiple losses; that is expected — note the same system against multiple rows.

Starter reference — common losses and the systems that close them

Observed lossSystem that closes itBook chapter
Kits pulled and not restockedKit-restock close-out discipline + weekly crib auditCh6 Plan / Ch9 Close Out
Bearing / part not where CMMS saysParts-consumption tagging at close-out + crib reconciliationCh9 Close Out
Shared tool missing / hunt delayShared-tool log + daily check-in/out at shift endCh8 Execute
Scheduled job cancelled with no noticeWritten cancellation protocol with 24h notice requirementCh7 Schedule
Job has no job planPlanner planning discipline + 1-week planning horizonCh6 Plan
Operator not available when crew arrivesScheduling coordination with operations + written handoffCh7 Schedule
Vendor meeting hijacks lead mid-shiftProtected calendar for leads + meeting whitelistCh7 Schedule
Close-outs say "Repaired. RTO."Close-out quality rubric + supervisor weekly auditCh9 Close Out
Break-in work displaces planned workFrozen-zone policy (48-72 hours)Ch7 Schedule
PMs slipPM kitting 48h ahead + escalation notificationsCh6 Plan / Ch7 Schedule
Notifications sit in NEW status24h triage commitment + weekly reject-pile reviewCh5 Identify
Operator anomalies never reportedOperator-driven reliability program + simple notification templateCh5 Identify

This table is a starter, not exhaustive. Your plant will produce losses that need bespoke systems. Write them down. The book's Parts II-V expand on each system listed here.

Your loss-to-system map

# (from Part 1)Loss (short)System that closes it
1
2
3
...
continue for all rows

Part 3 — System priority ranking

Aggregate the loss-hours-per-week by system. Most of your 15-20 loss rows will collapse onto 4-8 systems. That is good. It means the levers are fewer than the symptoms.

SystemLosses it closes (row #s)Total hours recovered per week (crew-wide)Notes on installation effort

The math that unlocks the budget conversation

Top 6 systems total recovered hours per week: _______

Multiplied by 48 working weeks per year: _______ hours

At your fully-loaded labor rate of $_______/hour: $_______ annual value

Translated to mechanic-equivalents (÷ 1,920 hrs/year): _______ mechanics

This is the sentence to bring to your plant manager:

"We are currently paying for [X] mechanics and extracting the productive output of [X minus Y]. If we install six specific systems over the next ninety days, we recover [Y] mechanic-equivalents of capacity. I am not asking for headcount. I am asking for ninety days of executive support for a frozen-zone policy, a kitting discipline, and a close-out standard."

Ray's numbers were:

  • 1,728 hours per year recoverable
  • ~1.5 mechanic-equivalents
  • Six systems, ninety-day plan
  • No hiring required

Yours will be different in specifics. The shape will be nearly identical.


Part 4 — Ninety-day installation sequence

For your top 6 systems, sketch a ninety-day installation order. Use this heuristic:

  • Weeks 1-2: Install the system whose loss is most visible to the crew. Building trust requires an early visible win.
  • Weeks 3-6: Install two systems that have the largest single recovery impact.
  • Weeks 7-10: Install two systems that depend on the first ones being in place (e.g., PM kitting depends on kit-restock discipline).
  • Weeks 11-12: Audit and reinforce. No new installation in the last two weeks. Make sure what you installed is holding.
System #Install duringVisible metric to track weekly
1Weeks 1-2
2Weeks 3-4
3Weeks 5-6
4Weeks 7-8
5Weeks 9-10
6Weeks 11-12 (reinforce + audit)

After ninety days

Redo your Follow-a-Crew Field Audit Sheet with a different crew. Expect a 5-10 percentage-point gain in wrench time for a first installation cycle. Less than that is diagnostic — probably means one of the systems did not actually get installed, only announced. Walk the floor and find out which.


From Fix the System by Ivan Getov. Companion to Chapter 2: The Job, and Why Most Plants Get It Wrong. getov.xyz/toolkit/fix-the-system/ch02/loss-list-system-priority. Free. No email required.