You finished the book. Here is what to do Monday morning.

Companion to: Fix the System, Chapter 28. Who uses it: the maintenance manager or supervisor who just finished the book and wants a clear starting point. When to use: once, at the beginning. Then follow the playbook's 90-day roadmap.


Step 1 — Identify Your Level (Day 1)

Answer honestly. Pick the one that fits today, not the one you are working toward.

Level 1 — Reactive: Reactive work above 30%. PM compliance below 70%. Backlog unmeasured or unknown. The schedule is directional at best.

Level 2 — Preventive: PM compliance 70–85%. Reactive work 15–30%. Schedule exists and is mostly followed. Backlog measured but not controlled.

Level 3 — Condition-Based: PM compliance above 85%. Reactive work below 15%. Backlog under 4 weeks. Starting to ask questions about CBM and MTTR.

My level today: ☐ Level 1 ☐ Level 2 ☐ Level 3


Step 2 — Pull Your Triggering Metric (Days 1–3)

One number. The one that is furthest from the benchmark for your level.

MetricWhere to Find ItBenchmark
PM complianceCMMS WO completion report≥85% (Level 2 entry)
Reactive work %Hours on unplanned WOs / total hours<30% (Level 2 entry)
BacklogOpen WOs × avg completion time<6 weeks (Level 2)
Schedule complianceScheduled WOs completed on day / total scheduled≥75% (Level 2)
Repeat failure rateWOs with same asset + same failure mode within 90 days<5/month (Level 2)

My biggest gap: _______________________ Current number: _______________________ Benchmark: _______________________


Step 3 — Open the Right Playbook (Day 3–5)

Match your gap to the playbook. Start with one. Only one.

If your gap is...Start with...Chapter
PM compliance below 85%Playbook 1: PM Compliance RecoveryCh15
Repeat failures above 5/monthPlaybook 2: Repeat Failure InvestigationCh16
Backlog above 6 weeksPlaybook 3: Backlog Growth ControlCh17
Reactive work above 30%Playbook 4: Reactive Work ReductionCh18
Schedule compliance below 75%Playbook 5: Schedule Compliance ImprovementCh19
Inspection completion below 80%Playbook 6: Inspection Compliance RecoveryCh20
Parts delays on >10% of WOsPlaybook 7: Spare Parts ManagementCh21
MTBF <500h on critical assetsPlaybook 8: Condition-Based MonitoringCh22
Availability below 95%Playbook 9: Downtime ReductionCh23
MTTR above 4h on critical assetsPlaybook 10: MTTR ReductionCh24

My playbook: _______________________


Step 4 — Week 1 Actions

  • Read the playbook chapter in full
  • Pull the data the playbook's trigger metric requires
  • Identify the top 3 contributors to the gap (the data will show you)
  • Download the companion worksheet from getov.xyz/toolkit
  • Tell one person — your manager, a shift supervisor, a planner — what you are starting and why

Step 5 — Weeks 2–4

  • Complete Part 1 of the companion worksheet (the audit / data collection step)
  • Start the 90-day roadmap at Days 1–30
  • Schedule a weekly 15-minute review of the triggering metric — same time, same format, every week
  • Do not open a second playbook yet

The One Rule

Finish a playbook before you open the next one.

A plant that runs three playbooks simultaneously at 40% completion each will show less improvement at month 6 than a plant that runs one playbook at 90% completion. The sequence matters less than the finish. Finish.


When You Are Ready for the Next Playbook

The current playbook is done when: the triggering metric has held at or above target for 60 consecutive days, the corrective actions are embedded in daily practice (not being monitored as a special project), and the crew no longer needs to think about it.

Then open the next one.


From Fix the System by Ivan Getov. getov.xyz/toolkit/fix-the-system/ch28/30-day-quick-start. Free. No email required.