Weekly Schedule Compliance Tracker

Letter & A4. Print-ready. Free, no email required.

← Back to toolkit · Browse by chapter

Complete one sheet per week. Code each miss the same day — context degrades fast. Complete Parts B and C at end of week.

Companion to: Fix the System, Chapter 19. Who uses it: the planner, scheduler, and maintenance manager during the weekly schedule review. When to use: every week during the Schedule Compliance Improvement playbook, and any week schedule compliance drops below target.


How to Use This Tracker

Complete one sheet per week. Fill in Part A daily as jobs are completed or missed. Code each miss the same day — context degrades fast. Complete Parts B and C at end of week.

Root cause codes:

CodeCause
PParts not staged at job start
OHOperations held equipment past release window
BIBreak-in displaced this job
SCScope mismatch — job took significantly longer than estimated
CRCrew availability — absent, reassigned, or called to other job
CCompliant — completed on scheduled day

Part A — Daily Work Order Log

Site / Zone: ___________________________ Week ending: ___________________________ Planner: ___________________________

#WO NumberAsset / DescriptionScheduled DayScheduled DurationActual CompletionCodeNotes
1Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
2Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
3Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
4Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
5Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
6Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
7Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
8Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
9Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
10Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
11Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
12Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
13Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
14Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
15Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
16Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
17Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
18Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
19Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____
20Mon / Tue / Wed / Thu / Fri_____ hrs_____ / _____

Add rows as needed. One row per scheduled WO.


Part B — Weekly Tally

Step 1: Count all scheduled WOs this week.

Total scheduled: _______

Step 2: Count WOs completed on their scheduled day (Code = C).

Total compliant: _______

Step 3: Calculate compliance.

Schedule Compliance = (Total compliant ÷ Total scheduled) × 100 = _______ %

Target: ≥85% | World-class: ≥95% | Trigger for Playbook 5: <75%


Root cause code tally (count each miss code):

CodeDescriptionCount% of misses
PParts not staged
OHOperations hold
BIBreak-in displaced
SCScope mismatch
CRCrew availability
Total misses100%

Top code this week: _______ Second code: _______

Action triggered: _______________________________________________


Part C — 4-Week Rolling Root Cause Trend

Fill in after each week. After 4 weeks, identify your top code and begin the fix from the Ch19 90-day roadmap.

CodeWeek 1Week 2Week 3Week 44-Wk Total% of All Misses
P
OH
BI
SC
CR
Compliance %

4-week top root cause: _______ Begin fix: See Ch19, Days 31–60 roadmap.


Planner's Notes

Use this section to note any patterns, one-time events (plant shutdown, holiday), or corrective actions taken this week.

_______________________________________________

_______________________________________________

_______________________________________________


From Fix the System by Ivan Getov. Companion to Chapter 19: Playbook 5 — Schedule Compliance Improvement. getov.xyz/toolkit/fix-the-system/ch19/schedule-compliance-tracker. Free. No email required.