Audit active inspection routes, code missed work, and verify the findings pipeline before compliance numbers count.

Companion to: Fix the System, Chapter 20. Who uses it: the maintenance manager, reliability engineer, planner, and route owner. When to use: at the start of the Inspection Compliance Recovery playbook, then monthly until route compliance stabilizes.

Plant: _______________________ Date: _______________________ Reviewed by: _______________________


PART 1 — Route Validity Audit

Complete one row per active route. Answer all four validation questions. Any "No" means the route needs corrective action before its compliance numbers count.

Route Name / IDAll Assets Active?Frequency Appropriate?Duration Accurate?Findings → WO within 24h?Action Required
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No
☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No☐ Yes ☐ No

Guidance:

  • All Assets Active? — Cross-check every stop against CMMS active asset list. Any decommissioned or relocated asset is a guaranteed miss. Delete it from the route immediately.
  • Frequency Appropriate? — Does the interval match the failure mode? Lube routes: weekly or monthly based on OEM. Vibration routes: monthly or bi-monthly. Visual rounds: daily to weekly. If unknown, default to OEM recommendation until condition data exists.
  • Duration Accurate? — Compare logged completion times over last 8 weeks against the scheduled time block. If average actual time exceeds scheduled time by more than 10%, the route is overfull.
  • Findings → WO within 24h? — Review last 10 findings from this route. Were WOs generated or no-action decisions documented within 24 hours? If not, the pipeline is broken.

PART 2 — Miss Coding Log (Last 8 Weeks)

Pull all flagged misses from the CMMS. Assign one primary code per miss. Tally codes at the bottom.

Codes:

  • IA — Invalid asset (decommissioned, relocated, never commissioned)
  • DF — Documentation failure (completed but not logged correctly)
  • TN — Time not available (crew pulled, no coverage)
  • FN — Finding logged, no action taken (route abandoned due to findings pipeline failure)
  • DS — Deliberately skipped
DateRouteMiss CodeNotes / ContextCorrective Action

Code Tally:

CodeCount% of Total Misses
IA — Invalid asset
DF — Documentation failure
TN — Time not available
FN — Finding no action
DS — Deliberately skipped
Total misses100%

Interpretation:

  • IA + DF together above 40%: Route management failure. Fix before any accountability conversation.
  • TN above 25%: Resource coverage problem. Review labor plan and break-in frequency (see Ch18 Playbook 4).
  • FN above 15%: Findings pipeline is broken. Technicians have learned that logging findings has no value.
  • DS above 20%: Crew engagement or consequence gap. Investigate before attributing to supervision failure.

PART 3 — 90-Day Compliance Tracking

Track weekly route completion across all routes. One row per week. Calculate compliance at the bottom.

WeekRoutes ScheduledRoutes CompletedMissesPrimary Miss Code(s)% Compliance
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13

Formula: % Compliance = Routes Completed ÷ Routes Scheduled × 100

Benchmarks:

  • Below 80%: Program not delivering value. Audit routes immediately.
  • 80–89%: Recovering. Identify remaining top miss codes and address in sequence.
  • 90–94%: Top quartile. Focus on findings pipeline quality.
  • 95%+: World-class. Maintain and audit route validity annually.

PART 4 — Findings Pipeline Audit

For each route, verify the findings pipeline is operational. Review last 10 findings per route.

RouteFinding DateFinding DescriptionWO Generated?Days to WO / No-Action DecisionAction Taken
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No

Findings Pipeline Summary:

  • Total findings reviewed: _______
  • WOs generated within 24h: _______ (___%)
  • No-action documented within 24h: _______ (___%)
  • No action, no documentation: _______ (___%) ← this number must be zero

If findings without documentation exceed 0%: Identify who owns the triage step and set a 24-hour response standard. Escalation path: planner reviews finding same day, routes to reliability engineer if no WO decision by end of shift.


From Fix the System by Ivan Getov. Companion to Chapter 20: Playbook 6 — Inspection Compliance Recovery. getov.xyz/toolkit/fix-the-system/ch20/inspection-route-audit. Free. No email required.